Introduction
The Buchanan Mall runs between Grove and Eddy Streets and consists of five blocks of green space, three playgrounds, a basketball court, and pedestrian paths. Through the Buchanan Mall Bulb-outs project, the San Francisco Public Works enhanced safety and connectivity for people walking to the mall and surrounding neighborhood by implementing improvements recommended in the Western Addition Community Based Transportation Plan. Improvements included sidewalk widening, new bulb-outs with ADA curb ramps, and utility and drainage relocation at the intersections of Buchanan Street and Golden Gate Avenue and Buchanan Street and Turk Street. This project connected the community to recreational spaces in the Western Addition neighborhood.
Project/Study Partners
This project was led by the San Francisco Public Works.
Cost and Funding
The Transportation Authority's Neighborhood Program funded the Buchanan Mall Bulb-outs with $300,000 in Prop K sales tax funds. This project was requested by Transportation Authority Board Member Dean Preston (District 5).
Project Timeline
-
July 2020 – December 2020
Design Engineering
-
January 2021 – March 2021
Advertise Construction
-
July 2021 – September 2021
Construction
-
January 2022 – March 2022
Project Completed and Open for Use
Resources
Buchanan Mall Bulb-outs Prop K funding request (PDF)
SFMTA’s Western Addition Safety Project Webpage
Western Addition Community-Based Transportation Plan
Contact
Michelle Woo, michelle.woo@sfdpw.org