Overview
Photo of the Sansome and Battery Bicycle Connections Project

Photo: SFMTA

Introduction

The SFMTA’s Sansome and Battery Connections Project improved walking and bicycling between the Embarcadero and the Financial District by providing an alternative route parallel to the Embarcadero corridor. Upgrades funded by the Neighborhood Program included signage, signal adjustments and striping to improve crosswalks, new bike lanes on Sansome, Battery, Vallejo, and Davis streets, and an additional crosswalk at the intersection of The Embarcadero, Sansome, and Chestnut streets.

Project/Study Partners

SFMTA

Goals 

  • Provide a new safe and attractive bikeway between Financial District and The Embarcadero
  • Improve safety for all who travel along the corridor
  • Reduce the number of conflicts between pedestrians, cyclists, and drivers on the corridor

Project Timeline

  • July 2018 – March 2019

    Planning and Conceptual Engineering

  • October 2018 – March 2019

    Environmental Studies

  • January 2019 – March 2019

    Design Engineering

  • Spring 2019

    Started Construction

  • Summer 2019

    Open for Use

  • Fall 2019

    Project Completed

Cost and Funding

This project was funded by the Transportation Authority’s Neighborhood Program at the request of Transportation Authority Board Chair Aaron Peskin (District 3). 

Resources

SFMTA’s Sansome & Battery Connections Project

Prop K transportation sales tax funding request (PDF)

Contact

Mark Dreger, SFMTA: mark.dreger@sfmta.com

Related programs

Image

Our Neighborhood Program supports neighborhood-scale planning efforts and project implementation in each supervisorial district.