Photo: SFMTA
Introduction
The SFMTA’s Sansome and Battery Connections Project improved walking and bicycling between the Embarcadero and the Financial District by providing an alternative route parallel to the Embarcadero corridor. Upgrades funded by the Neighborhood Program included signage, signal adjustments and striping to improve crosswalks, new bike lanes on Sansome, Battery, Vallejo, and Davis streets, and an additional crosswalk at the intersection of The Embarcadero, Sansome, and Chestnut streets.
Project/Study Partners
SFMTA
Goals
- Provide a new safe and attractive bikeway between Financial District and The Embarcadero
- Improve safety for all who travel along the corridor
- Reduce the number of conflicts between pedestrians, cyclists, and drivers on the corridor
Project Timeline
-
July 2018 – March 2019
Planning and Conceptual Engineering
-
October 2018 – March 2019
Environmental Studies
-
January 2019 – March 2019
Design Engineering
-
Spring 2019
Started Construction
-
Summer 2019
Open for Use
-
Fall 2019
Project Completed
Cost and Funding
This project was funded by the Transportation Authority’s Neighborhood Program at the request of Transportation Authority Board Chair Aaron Peskin (District 3).
Resources
SFMTA’s Sansome & Battery Connections Project
Prop K transportation sales tax funding request (PDF)
Contact
Mark Dreger, SFMTA: mark.dreger@sfmta.com