Proposition AA | Project Delivery

24th St BART Station Plaza Renovation

PROJECT DELIVERY

Prop AA is used to fund smaller, high-impact street repair and reconstruction, pedestrian safety, and transit reliability and mobility improvement projects throughout the city. To see whether Prop AA projects were recently completed in your neighborhood, please visit our Project News webpage and visit MyStreetSF, an interactive map, which shows all projects currently underway that are funded by, or prioritized for funding by the SFCTA, as well as those for which the SFCTA provides some level of oversight, in our role as Congestion Management Agency for San Francisco.

PROP AA VEHICLE REGISTRATION FEE | PROJECT DELIVERY STATUS

Project
Name
Phase Sponsor* Prop AA
Funds
Allocated
Total
Project
Cost
Status
STREET REPAIR AND RECONSTRUCTION CATEGORY
9th Street Pavement Renovation Construction Public Works

$2,216,627

$2,781,543 Open for use.
28th Ave Pavement Renovation Construction Public Works $1,169,843 $2,369,167 Open for use.
Chinatown Broadway Street Design Public Works $650,000 $8,199,591

Design funds allocated in November 2013, construction funds allocated in April 2016. Construction in progress. Anticipated open for use in summer 2017. 

Mansell Corridor Improvement Project Design, Construction SFMTA $2,527,852 $6,955,706 Design funds allocated in November 2013, construction funds allocated in December 2014 and April 2016. Construction in progress. Anticipated open for use in fall 2016. 
McAllister St Pavement Renovation Construction Public Works $1,995,132 $2,763,663 Open for use.
Dolores St Pavement Renovation  Construction Public Works $2,210,000 $3,230,263 Open for use.
    Subtotal $10,769,454 $26,299,933  
PEDESTRIAN SAFETY CATEGORY
Arguello Gap Closure Construction Presidio Trust $350,000 $1,015,715 Open for use.
Mid-Block Crossing on Natoma/8th Design, Construction SFMTA $365,000 $365,000

Open for Use.

Ellis/Eddy Traffic Calming Design SFMTA $337,450 $1,709,925 Design funds allocated in February 2014. Environmental review completed in winter 2016. Anticipated open for use in winter 2017.
Franklin and Divisidero Signal Upgrades Design, Construction SFMTA $896,750 $5,485,080

Design funds allocated in May 2015, construction funds allocated in February 2015. Design completed in early 2015. Construction to begin in late summer 2015 with all signals being operational by fall 2016.

Pedestrian Countdown Signals Construction SFMTA $1,380,307 $1,946,298 Open for use.
McAllister Street Campus Streetscape Design, Construction UC Hastings $1,845,206 $2,485,345 Open for use.
Webster Street Pedestrian Signals Design SFMTA $401,794 $1,760,000

Design funds allocated in November 2014. Design anticipated to be completed in summer 2016, followed by construction, with signals operational in fall 2017.

Gough St Pedestrian Signals Design SFMTA $300,000 $3,350,000 Design funds allocated in November 2015. Anticipated open for use in Winter 2018. 

Broadway Chinatown Streetscape Improvements

 Construction  Public Works  $1,029,839  8,199,591** Design funds allocated in November 2013, construction funds allocated in April 2016. Construction in progress. Anticipated open for use in summer 2017. 
Mansell Streetscape Improvements  Construction  Public Works $163,358  $6,955,706**  Design funds allocated in November 2013, construction funds allocated in December 2014 and April 2016. Construction in progress. Anticipated open for use in fall 2016.
Bulb-outs at WalkFirst locations  Design  SFMTA $491,757  $5,491,757 

Design funds allocated in April 2016. Design anticipated to be complete by December 2017, construction anticipated to begin in summer 2018. All locations anticipated open for use by fall 2020.

    Subtotal $7,561,460 $23,609,120  
TRANSIT RELIABILITY AND MOBILITY IMPROVEMENTS CATEGORY
Civic Center BART/Muni Bike Station Construction BART $248,000 $915,000 Open for use.
City College Pedestrian Connector Design, Construction SFMTA $933,000 $991,000

Open for use.

 
24th St Mission SW BART Plaza and Pedestrian Improvements Construction BART $713,831 $4,216,014 Open for use.
Elevator Safety and Reliability Upgrades Construction SFMTA $287,000 $2,734,500

Construction funds allocated in March 2016. All locations anticipated open for use in spring 2018.

Muni Bus Layover Area at BART Daly City Station

Construction SFMTA $507,980 $550,000 

Construction funds allocated in March 2016. Anticipated open for use in winter 2016.

Hunters View Transit Connection

Construction MOHCD $1,844,944 $1,844,944 Construction funds allocated in March 2014. Anticipated open for use in early 2017.
    Subtotal $4,534,805 $10,701,508  
    TOTAL $22,865,719 $60,610,561  

*Sponsor abbreviations include: Bay Area Rapid Transit District (BART);  Mayor's Office of Housing and Community Development (MOHCD); San Francisco Municipal Transportation Agency (SFMTA); University of California Hastings College of the Law (UC Hastings) .

**Project has also received allocations from Street Repair and Reconstruction category, so total project cost is excluded from Pedestrian Safety category subtotal to prevent double counting.