Transbay Transit Center and Caltrain Downtown Extension

Transbay Transit Center construction photo

Transbay Transit Center and tower visualizationThe Transbay Transit Center/Caltrain Downtown Extension (TTC/DTX) project is the critical centerpiece of a long-range visionary transportation plan that will transform downtown San Francisco and regional transportation well into this century. The project consists of three interconnected elements: 1) replacing the outmoded terminal with a modern terminal; 2) extending Caltrain 1.3 miles from Fourth and King streets to the new TTC at First and Mission streets, with accommodations for future high-speed rail; and 3) creating a new transit-friendly neighborhood with 3,000 new homes (35 percent of which will be affordable) and mixed-use commercial development. The total program budget is currently estimated at $4.1 billion in year-of-expenditure dollars. In May 2010 the Transbay Joint Powers Authority (TJPA) Board adopted a $1.6 billion budget for Phase 1 (TTC, pedestrian ramps, and the train box, which is the subterranean portion of the TTC building that will house the Caltrain and high-speed rail station). The current estimate for Phase 2 (DTX) is $2.5 billion.

The Prop K Expenditure Plan includes $270 million (in 2003 dollars) for the project. Of this amount, $237.7 million is designated as Priority 1 and $32.3 million as Priority 2 funds. The Expenditure Plan specifies that the downtown rail extension and the terminal, known as the Transit Center Building, are to be built as a single integrated project. To date, the Authority has allocated $147 million in Prop K funds to the project.

Design work continues on Construction Documents for the Transit Center Building.  Pelli, Clarke, Pelli Architects is proceeding with the implementation of the Risk and Vulnerability Assessment review recommendations. Completion of the 100% design is now scheduled for May 2013 to allow for those changes to occur. With Preliminary Engineering complete for the DTX, Parsons Transportation Group continued coordination with Caltrain and the California High-Speed Rail Authority (CHSRA).

The $187 million contact with Balfour Beatty for the construction of the buttress, excavation, and shoring of the new TTC building, is over 50% complete. In October 2012, TJPA awarded a $122 million contract to Shimmick Construction for the construction of the below-grade structure and work has commenced on the installation of micropiles and mud slab. It will be followed by contracts for Superstructure, Glazing, and in December 2013, main construction package Construction of the TTC is expected to be complete in late 2016. Bus operations are scheduled to commence in August 2017. Meanwhile, bus operations continue at the new temporary terminal.

The DTX is scheduled for completion in 2019; however, work is on hold due to a funding gap.

FACT SHEET

Download the most recent Transbay Transit Center fact sheet.

Project Schedule

TIMEFRAMEspacer image
ACTIVITY
April 2009   Transit Center Final Design begins
August 2010   Operations begin at Temporary Terminal
August 2010   Demolition of old terminal begins
December 2010   Shoring Wall and Buttress construction begins
February 2013   Sub-surface construction begins
April 2014   Superstructure construction begins
April 2015   Exterior Enclosure construction begins
April 2015   Interior Finishes begin
October 2017   Bus Operations begin