| Market Street Studies |
|
Better Market Street Pilot Improvements and Planning Process Underway!A collaborative effort between the Department of Public Works, the Planning Department, the Municipal Transportation Agency, the Mayor's Office of Workforce and Economic Development, and the Authority to make Market Street one of the City's most vibrant public spaces. Visit the Better Market Street Website or contact Michael Schwartz ( , 522-4823) for more details. FINAL STRATEGIC ANALYSIS REPORT ON TRANSPORTATION OPTIONS
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Project |
Phases for which funding is secured |
Status* |
|
|---|---|---|---|
| 1.1 | Relocate traffic signals to reduce the incidence of auto encroachment into the crosswalk | None | TBD |
| 1.2 | Restripe crosswalks |
Construction | Complete (with modifications) |
| 1.3 | Stripe advance limit lines at selected locations | Construction | Complete |
| 1.4 | Install pedestrian countdown timers | Construction | Complete |
| 1.5 | Install pedestrian-scale street signs | Construction | Complete |
| 3 | Develop and implement a new transit lane symbol and related signage | Construction | Complete |
| 4 | Install bike lanes between Van Ness and Eighth | Construction | Complete |
| 4 | Install bicycle lanes between Octavia and Van Ness Streets | Construction |
Complete |
| 5 | Implement proof-of-payment | Pilot project |
Ongoing |
| 6 | Change Market Street signal timing to improve transit performance | Planning | Ongoing |
| 7 | Improve wayfinding, directional, and advisory signage for motorists | Planning | Ongoing |
| 8 | Install new gore area signage [includes transit lane related signage, see Project 3] | Design, Construction | Design underway |
| 9 | Calm the ‘safety zone' | Design, Construction | Design underway |
| 10 | Install improved bicycle facility between Eighth Street and Justin Herman Plaza • Shared Lane Use Stencils |
Construction | Complete |
| 10 | Install improved bicycle facility between Eighth Street and Justin Herman Plaza • Bicycle Boxes at Intersections, other improvements |
Design, Construction | Design underway |
| 11 | Improve transit lane enforcement | Legislation |
|
| 12 | Require eastbound automobiles to turn right at Eighth Street during peak periods | None |
TBD |
*TBD = several proposed projects in the Market Street Action Plan require further study to determine whether implementation is necessary because other short-term projects may be sufficient to address the same issues in the corridor; early projects will be evaluated as outlined in the Market Street Action Plan.
Market Street Action Plan, Approved by the Authority Board
on February 24, 2004
The final product of the Market Street Study is the Action Plan, which describes a series of complementary, low cost improvements that can be implemented in the next one to five years to improve Market Street for transit users, cyclists and pedestrians while accommodating necessary motor vehicle traffic.
The Final Action Plan is a large file. If you have trouble opening it, click on the links below to go directly to specific sections, in smaller files.
Click here to view the Final Action Plan (3.8MB PDF)
Text-Only Version
Cover Page
Introduction
Recommendations
Project Monitoring, Funding Strategy,
Next Steps and Acknowledgements
In addition to the Final Action Plan, there were several other documents associated with the Market Street Study.
Technical Memoranda:
Bicycle lanes east of 8th Street
Bicycle facility east of 8th Street
Bicycle lanes from 8th to Octavia
Bicycle Origins and Destinations Report
Loading Bays and Illegal Parking Report
Transit Island Gore Point Signage Report
Transit Lane Violations Report
Transit Travel Time and Delay Report
Wayfinding and Transit Island Signing Report
Wayfinding Signage Digital Library Report
Other Documents:
Thanks to the City and County of San Francisco and a Transportation for Livable Communities Planning grant from the Metropolitan Transportation Commission who funded this study.