Download the Final Report, chapters of which are referenced below.
PRODUCT |
![]() |
SCHEDULE |
Existing Conditions Analysis: Assessment of the area's existing transportation system for deficiencies and potential effects of proposed development. |
Completed; see Chapter 2. |
|
Outreach: Engagement with surrounding communities and key stakeholders. |
Completed; see Chapter 4. |
|
Transit Service Planning and Parking Analysis: Analysis of the station's future transit needs, including space needed for LRT, BRT, local buses, and shuttles, and parking demand and supply. |
Completed; see Chapter 2. |
|
Station Access Planning and Design: Development of station design alternatives and evaluation of trade-offs. |
Completed; see Chapter 3. |
|
Design and Development Guidelines: Urban design guidelines for surrounding area, land use strategies to maximize transit ridership at the station, parking management strategies, and travel demand management strategies. |
Completed; see Chapter 6. |
|
Funding and Implementation Plan: Steps, agency roles, funding sources and coordination needed to move the project into environmental analysis, engineering design, and construction. |
Completed; see Chapter 7. |
|
Phasing Plan: Interim station access strategy as new land use and transportation projects come on-line incrementally. |
Completed; see Chapter 7. |
|
Final Report and Study Completion |
Final Report completed and adopted by the Transportation Authority Board on March 27, 2012. |